– A detailed copy of fire department activity is available upon request.
– As of October 12, 2016 NVFD responded to a total of 659 incidents. We responded to a total of 777 incidents in 2015, which was a 17% increase of 2014 and a 55% increase since 2013. 532 of those incidents were EMS related and 127 incidents were FIRE related. NVFD has provided mutual aid for 65 incidents, provided automatic aid 43 times, and received mutual aid for 23 incidents and automatic aid for 1 Incident. (Total MA received in 2013 was 13,.2014 was 15, 2015 was 22)
– NVFD’s average response time from time of call till time on scene is 3:36
o As mutual and automatic aid has increased, our overall response time has been increased on average
Fire Inspector I Prevention Report (As of September 13, 2016)
– 30 Annual Fire Inspections hay9,been completed
– 18 Hood/Duct/Alarm/Sprinkler Tests haye been.completed
– 66 Standby Events at Hard Rock Rocksino
Department News
New Ambulance – The new ambulance is set to be completed at the build plant on October 17th. It will then go to Pennsylvania for 7-10 days of final
install of equipment and stripping. It is my hope that the new ambulance will be in service the first week of November.
Hard Rock Rocksino & NVRC Stats – NVFD responded to 93 medical / 2 fire incidents at the Hard Rock and 61 medical I 1 fire incidents at NVRC Since January 1, 2016.
VILLAGE OF NORTHFIELDÂ ENGINEER’S REPORT – RICHARD S. WASOSKY, P.E., P.S.
Ledge Road Reconstruction Phase 1
Lockhart Concrete Co. has removed all of the poor subgrade soil and replaced it with limestone aggregate base. The entire roadway has been rough graded, and the south section of the road has been fine graded and proof rolled. The load transfer dowel bars have been installed along with the reinforcing steel in the eastbound lane from east of Salemi’s driveway to the corporation limit. All house connections, catch basins, manholes and yard drains have been installed. Paving of the eastbound lane is tentatively set for Friday night, October 15, 2016.
I will need Council’s approval to hire a concrete testing company to test the paving of the roadway and sidewalk concrete during construction. The testing firm charges $40.00 per hour per technician with a 4 hour minimum callout time plus $105.00 for one hour of the supervisor’s time per testing day. Time is charge portal to portal, and there is a $35.00 per day travel charge for their vehicle. Overtime is paid at 1.5 times the normal rate. Concrete cylinder testing is $15.00 per cylinder.
Presidential Subdivision Resurfacing
My technicians have completed their marking and measuring of the proposed curb and gutter repair areas. I have done further investigations of the project site and will start the final plan and specification work later this month.
Community Development Block Grant for Ledge Road Sidewalks
I received a copy of the signed contract for the sidewalk portion of the project on October 12, 2016. Summit County is requiring some additional forms and paperwork be completed during the project, as well as a project sign erected indicating the project is being partially funded with Community Development Block Grant money. I have made a detail of the sign needed. I will have Jason Walters have the signing company we use make up the sign and have the Service Department install it.