Northfield Center Trustee Meeting 6-22 – Springwood and Natalie Road Project

477

Meeting agenda and packet can be found here.

On June 22nd, the following legislation was approved: The Chair requests Resolution No. 20/06-22 A to: Approve the Alternative Tax Budget, which is to be submitted to the Office of the Summit County Fiscal Officer by no later than July 20, 2020  PASSED

The Chair requests Resolution No. 20/06-22 B to: Enact an additional annual levy of $5.00 per licensed motor vehicle to meet expenses of projects as outlined in ORC Section 4504.18. PASSED

The Chair requests Resolution No. 20/06-22 C to: Approve a Purchase Order, in the amount of $3,500.00, to be drawn from the 01-F-02 (Park and Recreation Improvement of Sites) Fund, payable to Nicks, for installation of the concrete pad/floor for the Beacon Hills Park pavilion. (This is part of the NatureWorks Grant Project.) Please note: This vendor was selected as the lowest and/or best bidder. PASSED

The Chair requests Resolution No. 20/06-22 D to: Approve a Purchase Order, in the amount of $1,000.00, to be drawn from the 01-A-26 (Other Expenses) Fund, payable to the Tidewater Creek Watershed Partners, for the Community Membership fee. PASSED

Northfield Center Springwood and Natalie Road Project

On June 24th the  trustees approved the creation of a Purchase Order, in the amount of $250,000.00, to be drawn from the 04-B-03 (Contracts), 04-C03 (Contracts), and 03-A-10 (Other Expenses) Funds, payable to Tri Mor Corporation, for completion of the Springwood and Natalie Road Reconstruction Project. This PO is in addition to the PO approved via Resolution No. 20/04-13A. The amount of the original PO was $312,987.41. The total portion of the project payable by Northfield Center is now estimated to be $557,514.84.

Editor’s Note:

The project was on hold due to adverse soil conditions. They needed to figure out what could be done and the new costs. The trustees decided to do the job right even though the costs are now much higher. If they did not make these adjustments, the road would have deteriorated much quicker than normal.

Meanwhile, drivers in the area are having to deal with very rough road conditions. 

Paving is on the schedule to start July 1st.