Wallings Road Bridge Project Update
The Wallings Road Bridge is expected to close April 7th, 2025 and remain closed for 365 days. The project is expected to reach completion October of 2026. Message boards will be placed on-site 2 weeks in advance of the closure to notify traffic. Please reach out to the Engineering Department at 440-838-4705 if you have any questions or concerns. The City of Broadview Heights Engineering Department will be holding and information session March 31st , 2025 5:00PM-7:00PM at City Hall in Council Chambers. This sessional will be open to any residents who have questions or concerns regarding the Wallings Road Bridge Project.
Any questions or concerns please call the Engineering Department at 440-838-4705 or watch for dates of upcoming information sessions.
Facebook Source: Broadview Heights Ohio